Which is NOT true regarding ELD programs for UST owners/operators?

  1. Approval submission must occur within 6 months of notification

  2. Implementation of the ELD program must happen within 18 months

  3. Testing must notify the local agency 48 hours in advance

  4. Emergency generator systems using ELD are exempt from notification

The correct answer is: Emergency generator systems using ELD are exempt from notification

In the context of the question regarding ELD (Enhanced Leak Detection) programs for UST (Underground Storage Tank) owners/operators, the statement that emergency generator systems using ELD are exempt from notification is not true. This is because all UST systems, including those using emergency generator systems, typically require some level of notification regarding their operations and monitoring status, including potential leak detection measures. Notification is a key component of regulatory compliance to ensure public safety and environmental protection. The other statements reflect true aspects of ELD program requirements. Specifically, following notification about an ELD program, the timeline for submitting approval is indeed constrained to six months. Additionally, actual implementation of the ELD program must occur within 18 months, which allows UST owners/operators sufficient time to develop and apply the necessary measures. Moreover, the requirement for testing notifications to the local agency 48 hours in advance ensures that regulatory bodies are informed about ongoing monitoring and can coordinate any necessary oversight or supportive activities.