What must occur if a UST system has a significant release detected?

  1. Immediate closure of the UST

  2. Notification to the local agency

  3. Installation of a new tank

  4. Increased frequency of inspections

The correct answer is: Notification to the local agency

When a significant release is detected in a UST system, it is critical to notify the local agency. This requirement ensures that appropriate regulatory bodies are informed of the potential environmental threat, allowing for timely investigation and remediation efforts. The local agency typically has protocols in place to assess the situation, determine the extent of the release, and oversee the necessary actions to mitigate any harm to the environment or public health. The notification process plays a fundamental role in managing hazardous materials and preventing further environmental contamination. It allows local authorities to coordinate resources and responses, ultimately enabling the appropriate assessment of risks involved associated with the release. In cases of significant releases, swift action and communication with regulatory bodies are essential to ensuring safety and compliance with environmental standards.