How long after conducting ELD testing must the test report be submitted to the local agency?

  1. 48 hours

  2. 30 days

  3. 60 days

  4. 90 days

The correct answer is: 60 days

The requirement to submit the test report for ELD (Electronic Leak Detection) testing to the local agency within 60 days is in accordance with regulatory guidelines that ensure prompt reporting and accountability in the management of underground storage tanks. Timely submission is critical as it enables regulatory bodies to monitor compliance effectively and address any potential environmental risks swiftly. Submitting the report within this timeframe allows agencies to take any necessary actions or follow-ups based on the findings of the test, ensuring that any leakage issues are dealt with promptly to prevent contamination and protect public health. This provision reflects a proactive approach in environmental regulation, as it balances the need for thorough testing with the necessity of timely information dissemination. The other timeframes mentioned are not aligned with the established regulations for ELD testing report submissions, emphasizing the importance of adherence to the correct 60-day requirement for maintaining environmental standards and safety.